Chapter I

General Electrical Knowledge

Master Electrician Practice study guide with diagrams.

General Electrical Knowledge

Learning Objectives

Upon completing this chapter, you will be able to:

Identify the components and sizing requirements for services and service equipment per Article 230
Apply the rules for separately derived systems, including transformers and generators, per Article 250 Part III
Perform feeder sizing calculations using the standard method of Article 220 and the optional method of 220.86
Select overcurrent protection devices with proper coordination and short-circuit current ratings
Apply motor circuit sizing rules from Articles 430 and 440, including branch-circuit, feeder, and short-circuit protection
Recognize the inspection points and common exam traps associated with commercial and industrial installations

1.1 Three-Phase Systems and Voltage Drop

Three-Phase Voltage Drop Flow — Colorado Master Electrician 2026 NEC Three-Phase Voltage Drop Flow NEC 215.2(A)(1) FPN — Feeder conductor sizing for 3-phase commercial/industrial CO-MST CH1 • 2026 NEC A B C SOURCE LOAD One-way distance L (feet) K FACTOR 12.9 Cu / 21.2 Al Ω-CM per 1000 ft LOAD CURRENT (I) Amperes NEC 220.5 — 125% continuous CONDUCTOR LENGTH (L) One-way feet Not round-trip for 3-phase CIRCULAR MILS (CM) Per Table 310.16 Chapter 9 Table 8 Three-Phase Voltage Drop Formula VD = √3 × K × I × L / CM √3 = 1.732 — accounts for 120° phase separation VD RESULT 3% or 5%? NEC 215.2(A)(1) FPN ≤ 3% — FEEDER ONLY Branch + feeder = 5% max ≤ 5% — FEEDER + BRANCH Total from source to outlet > 5% — INCREASE CONDUCTOR Re-calc with next larger CM per Table 310.16 ⚠ UNBALANCED LOAD Neutral current flows VD ≠ √3 formula MASTER TIP — NEC 215.2(A)(1) FPN: The 3%/5% voltage-drop recommendation is informational (FPN), not mandatory. However, PSI master-level questions expect you to size feeders using VD = √3·K·I·L/CM and verify against Table 310.16 ampacity adjustments. For motors: use 125% of FLA per NEC 430.22. For continuous loads: 125% per NEC 215.2(A)(1). When conductors run through high-ambient areas, apply Table 310.15(B)(1) correction factors before comparing CM. SDS (separately derived systems): VD calculated from SDS terminals to load per NEC 250.30(A) grounding requirements. Master Electrician Practice — NEC 215.2(A)(1) FPN three-phase voltage drop feeder sizing • Colorado DORA State Electrical Board 2026

A master electrician must understand three-phase power fundamentals to properly size conductors and equipment. In a balanced three-phase system, total power is calculated as P = √3 × V × I × power factor (for line-to-line voltage). For line-to-neutral calculations, use P = 3 × V × I × power factor.

Voltage drop is a performance consideration, not a safety requirement, except where specifically mandated (e.g., 210.19 for branch circuits, 215.2 for feeders, and 250.122 for equipment grounding conductors). The NEC recommends limiting voltage drop to 3% for branch circuits and 5% total (feeder plus branch circuit). For three-phase circuits, voltage drop is calculated using:

VD = (√3 × K × I × L) / CM

where K is the conductor resistivity constant (approximately 12.9 for copper, 21.2 for aluminum), I is the current in amperes, L is the one-way length in feet, and CM is the circular mil area of the conductor.

Exam trap: When calculating voltage drop for three-phase systems, do not use the single-phase formula (2 × K × I × L / CM). The √3 factor is often forgotten, leading to undersized conductors.


1.2 Services and Service Equipment (Article 230)

Service Conductor Sizing (230.42) — Colorado Master Electrician Service Conductor Sizing — NEC 230.42 Colorado Master Electrician · 2026 NEC · Multi-Step Calculation STEP 1 — Compute Load STEP 1 — Compute Load Article 220 load calc: • Lighting + receptacles (220.14) • Appliances + motors (220.14) • Demand factors (220.40+) → Total computed load (VA) STEP 2 — Min Ampacity 230.42(A)(1): Conductor ampacity ≥ computed load ÷ voltage (per phase) I ≥ VA / (V × √3) (3-phase) or VA / V (1-phase) STEP 3 — Select Conductor Table 310.16: • 75°C column (typical) • Temperature rating match • Terminals rated 75°C → AWG/kcmil from table STEP 4 — Dwelling 83% Rule 230.42(A)(2) — 1-family: If load ≥ 100A, ampacity may be 83% of Table 310.16 value I ≥ 0.83 × computed load Applies to service conductors only STEP 5 — GEC Sizing 250.66 — Grounding electrode: • Based on largest ungrounded service conductor (Table 250.66) • Not load-dependent → Copper or aluminum GEC STEP 6 — Verify & Document • Voltage drop (informative) • Short-circuit rating (110.9) • Overcurrent protection (230.90) • Ground-fault (230.95 if >1000A) → Code-compliant service 83% RULE Service Point — Utility to Service Disconnect (NEC 230.70) Conductors must be protected against physical damage (230.50) · Raceway / cable methods per 230.43 WORKED EXAMPLE — 3-Phase Service Given: 225A computed load, 208Y/120V, 3-phase, 4-wire service, dwelling unit Step 1: I = 225,000 VA / (208 × √3) = 625A → Step 2: 625A × 0.83 = 519A → Step 3: Table 310.16 75°C → 600 kcmil Cu (475A) or 2× 250 kcmil parallel Step 4: GEC per Table 250.66 → 1/0 Cu (for 600 kcmil) · Verify OCPD at 230.90 — max 800A per 240.4(B) Master Electrician Practice — NEC 230.42 service conductor sizing · Colorado DORA · 2026 NEC

A service is the conductors and equipment that deliver electric power from the utility to the service disconnecting means. The service point is the interface between utility and premises wiring.

Service conductors must be sized per 230.42 to carry the computed load per Article 220, with a minimum size of 8 AWG copper or 6 AWG aluminum for overhead service conductors (230.23). Underground service conductors have no minimum size but must be sized for the load.

Service disconnecting means (230.70–230.85) must:

Disconnect all ungrounded conductors simultaneously
Be rated at least the computed load, but not less than the minimum ampacity of the service conductors
Be located at a readily accessible point nearest the point of entrance of the service conductors
Have a maximum of six disconnects (230.71) unless a single main disconnect is provided

Service overcurrent protection (230.90) must protect the service conductors against overload and short circuit. The rating must not exceed the ampacity of the conductors, except where the next standard size (per 240.6) is permitted when the ampacity does not correspond to a standard rating.

Exam trap: For services with multiple disconnects, each disconnect must be rated for the load it serves, but the total of all disconnects must not be less than the computed load. The 6-disconnect rule counts each handle, not each enclosure.

Inspection point: Verify that the service disconnecting means is marked "Suitable for Use as Service Equipment" when it is the only disconnecting means, per 230.66.


1.3 Separately Derived Systems (Article 250 Part III)

A separately derived system is a premises wiring system whose power is derived from a source of electrical energy (e.g., transformer, generator) that has no direct electrical connection to the supply conductors from another system.

Bonding requirements (250.30):

The system bonding jumper connects the grounded conductor to the equipment grounding conductor at the source or at the first disconnecting means
The grounded conductor must be connected to the equipment grounding conductor at only one point (the source or first disconnect, not both)
The system bonding jumper must be sized per Table 250.102(C)(1) based on the area of the largest ungrounded conductor

Grounding electrode conductor (250.30(A)(4)): For a separately derived system, a grounding electrode conductor must connect the grounded conductor to a grounding electrode. The size is based on Table 250.66, using the area of the largest ungrounded conductor. The grounding electrode can be a building steel electrode, a concrete-encased electrode, or a ground rod, but the connection must be made at the same point as the system bonding jumper.

Generator applications: A generator with a transfer switch that opens the neutral is a separately derived system. If the transfer switch does not switch the neutral (solid neutral), the generator is not separately derived, and the neutral remains bonded at the service.

Exam trap: For a transformer supplying a panelboard, the neutral must be bonded to the equipment grounding conductor at the transformer (or first disconnect) and must NOT be bonded again at the panelboard. A common code violation is installing a bonding screw in the panelboard neutral bar when the transformer is the source.


1.4 Feeder Sizing and Load Calculations (Article 220)

Feeder Load Calc Path — 220 + 215 Master Depth Feeder Load Calc Path — NEC 220 + 215 Colorado Master Electrician · 2026 NEC · DORA/PSI · Open-Book Theory STEP 1 — GATHER LOADS Lighting / Receptacles 220.42 demand factors VA from floor area × unit load Appliances ≥ 4 units 220.53 — 75% demand factor Dryers 220.54 — 5000 VA each Ranges / Cooktops 220.55 — Table demand Motors / Other 430.24 + 220.50, 220.61 STEP 2 — APPLY DEMAND Method Selection Standard 220.40 Optional 220.82 / 220.84 Demand Load Stack (VA) Lighting demand Appliance 75% demand Dryer demand Range demand Motor demand = Total Demand VA STEP 3 — SIZING (215.2) Minimum Ampacity I = VA ÷ (V × √3) 3-phase · 215.2(A)(1) ≥ 125% continuous + 100% noncont. Conductor Selection Per Table 310.16 Apply 310.15(C) adjustments Termination Temp Rating 110.14(C) — 75°C column Voltage Drop Check Recommended ≤ 3% feeder STEP 4 — OCPD (215.3) OCPD Rating ≥ Noncontinuous + 125% cont. 215.3 · Next standard size per 240.6(A) Feeder Protection Must protect feeder per its ampacity after adjustments Ground-Fault Protection 230.95 — 1000A+ (if service) Neutral / Ground 220.61 · 250.66 sizing Continuous loads at 125% · Noncontinuous at 100% · Neutral loads per 220.61 · Adjustments per 310.15 Master Electrician Practice — NEC 220 feeder loads + 215.2 ampacity / 215.3 OCPD · 2026 NEC

The standard method (220.40–220.61) applies to all installations unless the optional method is permitted.

General lighting load (Table 220.12): For dwelling units, 3 VA/ft²; for commercial (banks, offices), 3.5 VA/ft²; for warehouses, 1.25 VA/ft². These are minimum values.

Receptacle loads (220.14): For non-dwelling occupancies, receptacles are calculated at 180 VA each. The first 10 kVA of receptacle load is permitted at 100% demand factor; the remainder at 50% (220.44).

Feeder sizing (215.2): The feeder must have an ampacity not less than the computed load, and must be sized to accommodate voltage drop. The minimum feeder size must also be adequate for the largest motor plus 125% of the remaining load (430.24).

Optional method for feeders (220.86): For existing dwelling units with electric space heating, air conditioning, or both, the feeder can be sized using the optional calculation. The computed load is the larger of the heating or cooling load, plus the first 8 kVA of remaining load at 100%, and the remainder at 40%.

Exam trap: When calculating a feeder for a commercial kitchen, the demand factors of Table 220.56 apply. Do not apply the dwelling unit demand factors of 220.52 to commercial occupancies.


1.5 Overcurrent Protection and Coordination (Article 240)

Standard ampere ratings (240.6): 15, 20, 25, 30, 35, 40, 45, 50, 60, 70, 80, 90, 100, 110, 125, 150, 175, 200, 225, 250, 300, 350, 400, 450, 500, 600, 700, 800, 1000, 1200, 1600, 2000, 2500, 3000, 4000, 5000, 6000.

Overcurrent device location (240.21): Overcurrent devices must be located where conductors receive their supply, with exceptions for taps (240.21(B) for feeders, 240.21(C) for transformer secondaries).

Transformer secondary protection (240.21(C)): The primary protection must not exceed 125% of the primary rated current (for transformers with 9% or less impedance). If primary protection exceeds this, secondary protection is required within 10 feet of the transformer.

Coordination (240.12): Where required by other articles (e.g., 700.27 for emergency systems, 701.27 for legally required standby systems), overcurrent devices must be coordinated so that a fault on a branch circuit clears only the branch circuit device, not the feeder or main.

Short-circuit current rating (SCCR): Equipment must be rated for the available fault current at its terminals (110.10). A master must verify that the interrupting rating of the overcurrent device exceeds the available fault current.

Exam trap: The 10-foot tap rule (240.21(B)(1)) requires the tap conductor ampacity to be at least 10% of the rating of the overcurrent device protecting the feeder. A common error is using 25% (which applies to the 25-foot tap rule).


1.6 Motors and Generators (Articles 430 and 445)

Motor branch-circuit conductors (430.22): Must have an ampacity of at least 125% of the motor full-load current (FLC). For continuous duty motors, use Table 430.247 (DC), 430.248 (single-phase), or 430.250 (three-phase) to determine FLC.

Motor branch-circuit short-circuit and ground-fault protection (430.52): The rating must not exceed the percentages in Table 430.52:

Non-time-delay fuse: 300% of FLC
Dual-element time-delay fuse: 175% of FLC
Inverse-time circuit breaker: 250% of FLC

If these values do not correspond to standard ratings, the next higher standard size is permitted (430.52(C)(1) Exception 1).

Motor feeder conductors (430.24): Must be sized at 125% of the largest motor FLC plus the sum of the FLC of all other motors on the feeder.

Motor feeder overcurrent protection (430.62): The feeder protection must be sized at the largest branch-circuit protection device plus the sum of the FLC of all other motors.

Generators (Article 445): Generator conductors must be sized at 115% of the generator nameplate current rating (445.13). Overcurrent protection must be provided per 445.12, but if the generator is a separately derived system, the bonding and grounding rules of 250.30 apply.

Exam trap: For a motor with a nameplate full-load current that differs from the table value, use the table value for conductor sizing and the nameplate value for overload protection (430.32). Mixing these up is a classic error.


1.7 Commercial and Industrial Installations

Panelboards (408.36): Must have overcurrent protection on the supply side, with the protection rating not exceeding the panelboard rating. Exception: a panelboard supplied by a transformer with primary protection per 240.21(C) may be protected at the primary.

Switchboards and switchgear (408.3): Must have bus bars rated for the available fault current. The equipment grounding conductor must be sized per Table 250.122.

Wiring methods (Article 300): In commercial occupancies, conduit fill must not exceed 40% for three or more conductors (Chapter 9, Table 1). For industrial installations, cable trays (Article 392) have specific ampacity adjustment factors per 392.80.

Receptacle placement (210.52 for dwellings; 210.62 for commercial): Commercial occupancies must have receptacles within 25 feet of permanently installed equipment (210.63). Service areas require at least one receptacle.

Inspection point: Verify that all equipment grounding conductors are properly terminated and that no bonding screw or jumper is installed in a panelboard that is supplied by a separately derived system (other than the source).


1.8 Code Navigation

TopicArticle/Table
ServicesArticle 230
Service disconnect230.70–230.85
Service conductor sizing230.42
Separately derived systems250.30
System bonding jumper sizeTable 250.102(C)(1)
Grounding electrode conductorTable 250.66
Load calculations (standard)Article 220, Part III
Lighting load densitiesTable 220.12
Receptacle load (non-dwelling)220.14(H), 220.44
Feeder sizing215.2
Optional feeder method220.86
Standard OCPD ratings240.6
Transformer secondary protection240.21(C)
Motor FLC tables430.247, 430.248, 430.250
Motor branch-circuit protection430.52, Table 430.52
Motor feeder sizing430.24
Motor feeder protection430.62
Generator conductors445.13
Panelboard protection408.36
Conduit fillChapter 9, Table 1

1.9 Inspection and Supervision Points

When supervising an installation, a master electrician must verify:

83.Service entrance: The service disconnect is properly rated, accessible, and marked. The grounding electrode conductor is continuous and properly connected to an acceptable electrode.
84.Separately derived systems: The neutral is bonded at the source only, and a grounding electrode conductor is installed to an approved electrode.
85.Feeder sizing: Conductors are sized per the computed load, with voltage drop considered for long runs.
86.Overcurrent protection: Device ratings match the calculated values, and interrupting ratings exceed the available fault current.
87.Motor circuits: Branch-circuit conductors are sized at 125% of FLC, and overload protection is based on nameplate current.
88.Panelboards: No double bonding of neutrals to equipment grounds in subpanels supplied by separately derived systems.

1.10 Common Exam Traps

Using single-phase voltage drop formula for three-phase circuits
Bonding the neutral at a subpanel supplied by a separately derived system
Sizing motor conductors from the nameplate instead of the table FLC
Applying dwelling demand factors to commercial loads
Forgetting the 125% factor for continuous loads (210.19(A)(1))
Using the 25-foot tap rule percentages for a 10-foot tap
Sizing generator conductors at 100% instead of 115% of nameplate
Failing to account for the largest motor when sizing feeders (430.24)

Summary

Master-level knowledge of general electrical theory requires fluency in three-phase calculations, service and separately derived system rules, feeder sizing, overcurrent coordination, and motor applications. The NEC is organized to support these calculations, but the master must know where to look and how to apply the tables and exceptions correctly. On the exam, always verify the article number, check the table notes, and confirm whether an exception applies before selecting a final answer.

Preparing for the Colorado Master Electrician license?

See the full licensing path, exam format, eligibility and application steps.

Read the Colorado Master Electrician guide

Ready to test this chapter?

Practice with exam-aligned questions and timed simulations.

Start Practicing Free