Chapter I

Definitions, Theory, and Plans

Master Electrician Practice study guide with diagrams.

Definitions, Theory, and Plans

Learning Objectives

Upon completing this chapter, you will be able to:

4.Distinguish between service, feeder, and branch-circuit definitions as they apply to commercial and industrial installations.
5.Apply the fundamental theory of 3-phase power systems, including wye and delta configurations, to calculate loads and size conductors.
6.Identify the requirements for separately derived systems, including transformers and generators, and their grounding and bonding obligations.
7.Perform code-required feeder and service calculations using the standard and optional methods.
8.Navigate the NEC efficiently by locating definitions, tables, and calculation methods by article number.
9.Recognize common exam traps related to terminology, voltage drop, and overcurrent protection coordination.

1.1 The Hierarchy of Power Distribution: Branch Circuit, Feeder, Service

The Service-Feeder-Branch Hierarchy — Master Electrician Practice, NEC 2026 Service → Feeder → Branch Circuit Hierarchy TX Master Electrician · NEC 2026 · TDLR/PSI Open-Book · Chapter 1 — Definitions & Theory Utility Transformer Primary: 13.8 kV / 480V NEC 450.3 Transformer Protection Service Conductors Sized per NEC 230.42 + Table 310.16 (75°C col) Service Disconnect NEC 230.70 — 6-Disconnect Rule Service Point = utility side Feeder Conductors NEC 215.2 — 125% continuous + voltage drop NEC 210.19(A) Panelboard NEC 408.36 — OCPD required Bus rating ≥ feeder ampacity SERVICE POINT NEC 230.70: Service begins at first disconnect. Grounding per NEC 250.66 (GEC sizing). Master Depth: Available fault current → interrupting rating per NEC 110.9 Ampacity Adjustments: 310.15(C) — 4+ CCC derate + 310.15(B) ambient correction Voltage Drop (Master): VD = 2KIL/CM (single-phase) VD = 1.732KIL/CM (three-phase) Grounding Electrode: 250.66 — GEC sized to largest service conductor, Table 250.66 Motor Circuits: 430.22 — 125% of FLA continuous Branch Circuits — NEC 210 210.23(A) — 15/20A multi-outlet 210.23(B) — 30A fixed appliances 210.23(C) — 40/50A fixed + cooking 210.52 — receptacle spacing Optional Method — NEC 220.84 General load: 3 VA/ft² (220.84(A)) + 1,500 VA each small-appliance + 1,500 VA laundry (220.84(A)) + appliance nameplates (220.84(B)) Demand: first 10 kVA @ 100% remainder @ 40% (220.84(C)) Master Depth — Multi-step calc: 1. Compute total connected load 2. Apply demand factors 3. Size feeder at 125% continuous Master Electrician Practice — NEC 2026 service/feeder hierarchy · NEC 230.42, 215.2, 210.23, 220.84

A master electrician must think in terms of system architecture, not just individual circuits. The NEC defines three distinct levels of power distribution, and misapplying these terms is a common source of exam errors.

Branch Circuit (Article 100): The conductors between the final overcurrent device (OCPD) protecting the circuit and the outlet(s) or equipment. This includes the circuit supplying a single motor, a lighting panelboard's individual circuits, or a dedicated receptacle. Branch circuits are classified by the rating of the OCPD (15, 20, 30, 40, 50 amperes) per 210.3.

Feeder (Article 100): All circuit conductors between the service equipment, the source of a separately derived system, or other power supply source, and the final branch-circuit OCPD. A feeder supplies a panelboard, a motor control center, or a subpanel. The distinction is critical: a feeder does not directly supply loads; it supplies a distribution point.

Service (Article 100): The conductors and equipment for delivering electric energy from the utility supply system to the service disconnecting means. The service point is the interface between the utility and the premises wiring. The service-entrance conductors run from the service point to the service disconnecting means. Service equipment (230.62) includes the necessary disconnecting means, OCPDs, and enclosures.

Exam Trap: A common question asks whether a conductor feeding a subpanel is a feeder or a branch circuit. If it terminates at the main breaker of a subpanel, it is a feeder. If it terminates at a single OCPD protecting a motor, it is a branch circuit, even if it is long and large.


1.2 Three-Phase Systems: Theory for the Master

3-Phase Wye and Delta — Master Depth Theory 3-Phase Wye and Delta — Master Depth TX-MST-KNOW Ch1 Definitions, Theory & Plans — 2026 NEC / NFPA 70, TDLR/PSI WYE (Y) — 480/277V or 208/120V H1 H2 H3 N A B C V_LL = V_LN × √3 V_LL = V_LN × √3 → 208V = 120V × 1.732 | 480V = 277V × 1.732 DELTA (Δ) — 480V or 240V A B C I_phase I_LINE = I_PHASE × √3 | No neutral | V_LL = V_PHASE Master Point: Wye steps voltage down with neutral for 120V/277V loads; Delta delivers higher current at constant voltage — no neutral, industrial loads Master Electrician Practice — NEC 2026 Ch1 Definitions, Theory & Plans (TX-MST-KNOW) | TDLR/PSI Open-Book

The master exam assumes fluency in 3-phase calculations. You must understand the relationship between line and phase values in both configurations.

Wye (Y) Systems: The common point (neutral) is grounded. Line-to-neutral voltage is the phase voltage. Line-to-line voltage is √3 (1.732) times the phase voltage. For a 208Y/120-volt system, the line-to-line voltage is 208 V, and each phase-to-neutral is 120 V. The current in each line equals the phase current.

Delta (Δ) Systems: No neutral point is derived from the transformer secondaries. Line-to-line voltage is the phase voltage. The line current is √3 times the phase current. A common commercial delta is 240-volt, 3-phase, 3-wire. A high-leg delta (240/120 V, 4-wire) has a center-tapped transformer on one phase, providing a 120-volt single-phase service. The high-leg (B phase) is 208 V to neutral and must be identified with orange tape or marking at every point where a connection is made (110.15).

Power Calculations:

Single-phase: P = V × I × pf (power factor)
Three-phase: P = √3 × V_line × I_line × pf
For motors, use the full-load current (FLC) from Tables 430.247 through 430.250, not the nameplate rating, for conductor and OCPD sizing.

Voltage Drop (210.19(A) Informational Note, 215.2(A)(1) Informational Note): The NEC does not mandate a specific voltage drop percentage for general circuits, but the informational notes recommend 3% for branch circuits and 5% total (feeder plus branch). For a master, this is a design responsibility. The formula for 3-phase is: VD = (√3 × I × L × R) / 1000, where R is the conductor resistance per 1000 feet from Chapter 9, Table 8.

Exam Trap: The exam will provide a motor FLC from Table 430.250, not the nameplate. Using the nameplate current will result in undersized conductors. Always use the table values for conductor sizing.


1.3 Services and Service Equipment

Article 230 governs services. A master must know the minimum requirements for commercial services.

Number of Services (230.2): A building can be served by only one service, except for specific allowances: fire pumps, emergency systems, optional standby systems, multiple occupancy buildings, and capacity requirements. Each service disconnecting means must be grouped (230.72).

Service Disconnecting Means (230.70, 230.71): The service disconnecting means must be at a readily accessible location nearest the point of entrance of the service conductors. For a multi-occupancy building, each occupant must have access to their disconnecting means. The maximum number of disconnects per service was historically six; however, the 2020 NEC and subsequent editions require a single service disconnect for each service, unless the installation qualifies for specific exceptions (e.g., multiple disconnects for large capacity or utility requirements). Verify the exact language in 230.71 for the current edition.

Service Overcurrent Protection (230.90): Each ungrounded service conductor must have an OCPD. The rating must not exceed the ampacity of the conductor. However, 230.90(A) Exception 1 allows the next higher standard OCPD rating if the ampacity does not correspond to a standard rating and is less than 800 amperes.

Grounding Electrode System (250.50): All grounding electrodes present at the building must be bonded together. The service must have a grounding electrode conductor (GEC) sized per Table 250.66. For a service using paralleled conductors, the GEC is sized based on the largest ungrounded conductor.

Inspection Point: Verify that the service disconnect is marked as "Suitable for Use as Service Equipment" (230.66). Check that the grounded conductor (neutral) is bonded to the enclosure and the grounding electrode conductor only at the service disconnecting means (250.24). A neutral-ground bond downstream of the service is a violation and creates a parallel path for neutral current.


1.4 Separately Derived Systems: Transformers and Generators

Separately Derived System Grounding — NEC 250.30(A) Master Depth Separately Derived System Grounding — NEC 250.30(A) System Bonding Jumper at First Disconnect • GEC to Electrode • Master Depth Transformer Secondary 480V → 120/208V 4-Wire Wye NEC 250.30(A)(1) Phase A Phase B Phase C Neutral (Grounded) First Disconnect (Service Equipment) NEC 250.30(A)(2) Bonding Jumper 250.30(A)(1) EGC Equipment Grounding Conductor Panelboard (Load Side) Branch Circuits NEC 250.30(A)(4) GEC 250.66 sizing Electrode Master Points • SDS neutral bonded AND grounded at first disconnect • GEC sized per Table 250.66 based on secondary conductors • EGC separate from neutral beyond this point (250.30(A)) ⚠ Common Violation Bonding neutral at both source AND disconnect creates parallel path Master Electrician Practice — NEC 250.30(A) Separately Derived System Grounding • 2026 NEC / TDLR / PSI Source Load N Bus EGB GEC sizing: use largest secondary conductor per Table 250.66

A separately derived system (SDS) is a premises wiring system whose power is derived from a source of electric energy or from a transforming device, and that has no direct electrical connection (including a solidly grounded circuit conductor) to supply conductors originating in another system (Article 100).

Examples: A transformer with a secondary that has no solid connection to the primary neutral; a generator with a transfer switch that opens the neutral; an uninterruptible power supply (UPS) with an isolation transformer.

Grounding and Bonding (250.30): The SDS must have its grounded conductor (neutral) connected to a grounding electrode conductor and a grounding electrode at the source (the transformer or generator location). The system bonding jumper connects the equipment grounding conductor and the grounded conductor at the source. This is the only place the neutral is bonded to ground in an SDS.

Transformer Installations (450.3): Overcurrent protection for transformers must comply with Table 450.3(B). For a transformer with primary current of 9 amperes or more, the primary OCPD must be set at 125% of the primary current. If the secondary is not protected, the primary device must be sized at 125% of the primary current, and the secondary conductors must be protected by a secondary OCPD. For transformers over 600 V, refer to Table 450.3(A).

Generator Installations (445, 700, 701): Generators used for emergency systems (Article 700) or legally required standby systems (Article 701) have specific requirements. The transfer switch must be listed for the purpose. For a generator that is an SDS, the neutral must be switched if the generator is a separately derived source. If the generator is not an SDS (i.e., the neutral is solidly connected to the utility neutral), the generator frame must be bonded to the equipment grounding conductor, but the neutral is not bonded at the generator.

Inspection Point: On a transformer, verify that the secondary neutral is bonded to the transformer enclosure and the GEC. Check that the primary and secondary conduits are bonded. Look for the presence of a grounding electrode at the transformer location, not just a connection back to the service.


1.5 Feeder and Service Load Calculations

Article 220 provides the calculation methods. A master must be able to perform both the standard method (Part III) and the optional method (Part IV) for dwellings, and the standard method for commercial.

General Lighting Load (Table 220.12): For commercial occupancies, the unit load is 1.2 VA/ft² for general lighting. For dwelling units, it is 3 VA/ft². For hospitals, it is 2 VA/ft². These values are minimums.

Receptacle Loads (220.14): For general-purpose receptacles in commercial buildings, the load is calculated at 180 VA per receptacle strap. This is a significant difference from dwellings, where receptacle loads are included in the general lighting load.

Demand Factors (Table 220.42): For dwelling units, the general lighting load is subject to demand factors: the first 3,000 VA at 100%, and the remainder at 35%. For commercial, the general lighting load is typically taken at 100% unless specific demand factors apply.

Motor Loads (430.24): When a feeder supplies multiple motors, the feeder conductor must be sized at 125% of the largest motor FLC plus 100% of the FLC of all other motors. The feeder OCPD must be sized per 430.62: the largest motor's branch-circuit OCPD rating plus the sum of the FLCs of the other motors.

Optional Method for Dwelling (220.82): This method allows a smaller service for a dwelling unit. It uses the general lighting load at 3 VA/ft², plus 1,500 VA for each small-appliance and laundry circuit, plus the nameplate ratings of appliances. The first 10,000 VA is at 100%, and the remainder is at 40%. This is a common exam calculation.

Optional Method for Commercial (220.86): This method is available for commercial occupancies with a connected load of 3,000 kVA or less, or for a feeder with a calculated load of 1,000 kVA or less. It uses a demand factor based on the total connected load.

Exam Trap: When calculating a service for a commercial building, do not forget to include the 25% additional load for the largest motor (430.24) and the 125% factor for continuous loads (210.19(A)(1)). A continuous load is one where the maximum current is expected to continue for 3 hours or more.


1.6 Overcurrent Protection Coordination

Article 240 covers overcurrent protection. A master must understand the difference between a fuse and a circuit breaker, and the concept of selective coordination.

Selective Coordination (240.12): Where required by other articles (e.g., 700.28 for emergency systems, 701.27 for legally required standby systems), overcurrent devices must be selected so that a fault on a branch circuit clears the branch OCPD without opening the feeder OCPD. This is achieved by ensuring the time-current curves of the devices do not overlap.

Transformer Secondary Protection (240.21(C)): The tap rules for transformer secondaries are specific. A secondary conductor can be protected by a primary OCPD if the primary device is sized at 125% of the primary current and the secondary conductors have an ampacity at least 1/3 of the primary OCPD rating. This is the "10-foot tap" rule.

Inspection Point: Verify that all OCPDs are properly identified as to their interrupting rating (110.9). A device with an insufficient interrupting rating is a serious hazard. Check that the OCPD is not installed in the grounded conductor (240.22), except where the device opens all ungrounded conductors simultaneously.


1.7 Code Navigation: Where to Find It

ConceptNEC Location
Definitions (Service, Feeder, Branch Circuit, SDS)Article 100
Branch Circuit RequirementsArticle 210
FeedersArticle 215
ServicesArticle 230
Overcurrent ProtectionArticle 240
Grounding and BondingArticle 250
Wiring MethodsArticles 300–398
Motors and GeneratorsArticle 430
TransformersArticle 450
Emergency SystemsArticle 700
Legally Required Standby SystemsArticle 701
Optional Standby SystemsArticle 702
Load CalculationsArticle 220
Conductor Ampacity TablesTable 310.16 (75°C column for terminations)
Conductor ResistanceChapter 9, Table 8
Motor FLC TablesTables 430.247–430.250
Transformer OCPD TablesTable 450.3(A) and (B)
Grounding Electrode Conductor SizingTable 250.66
Equipment Grounding Conductor SizingTable 250.122

1.8 Inspection and Supervision Points

As a master, you are responsible for the work of others. On site, verify:

69.Termination Temperatures: Conductors are sized using the 75°C column of Table 310.16 unless the equipment terminals are rated for 90°C. Most standard breakers and panelboards are rated at 75°C.
70.Bonding at Services: The neutral is bonded to the enclosure and the GEC at the service disconnect, and only there.
71.High-Leg Marking: The B phase in a high-leg delta is orange-tagged at all accessible points.
72.Transformer Grounding: The secondary neutral is bonded to the transformer enclosure and a grounding electrode.
73.OCPD Ratings: The interrupting rating of the devices is sufficient for the available fault current.
74.Working Clearance (110.26): Equipment is accessible with the required clearance (typically 36 inches deep, 30 inches wide, and 6.5 feet high).

1.9 Common Exam Traps

Using nameplate current instead of Table FLC for motors. Always use Tables 430.247–430.250 for conductor and OCPD sizing.
Forgetting the 125% factor for continuous loads. A continuous load is 3 hours or more.
Sizing the neutral for the full unbalanced load. The neutral must be sized for the maximum unbalanced load, but it can be smaller than the phase conductors in some cases.
Confusing the grounding electrode conductor with the equipment grounding conductor. The GEC connects the system to the earth; the EGC connects the equipment to the system ground.
Applying the optional method for a dwelling incorrectly. The 40% demand factor applies to the remainder over 10,000 VA, not the entire load.
Forgetting the high-leg voltage. In a 240/120 V high-leg delta, the high-leg to neutral is 208 V, not 120 V. Single-phase loads must not be connected to the high-leg.

Summary

This chapter has covered the foundational definitions, 3-phase theory, service requirements, separately derived systems, load calculations, and overcurrent protection coordination. A master electrician must be able to navigate the NEC quickly and accurately, applying these principles to real-world installations. The exam will test not only your memory of the code text but your ability to apply it to complex, multi-system installations. Mastery of these topics is essential for the license that allows you to pull permits, supervise work, and take responsibility for the safety of the public.

Preparing for the Texas Master Electrician license?

See the full licensing path, exam format, eligibility and application steps.

Read the Texas Master Electrician guide

Ready to test this chapter?

Practice with exam-aligned questions and timed simulations.

Start Practicing Free