Equipment for General Use
Master Electrician Practice study guide with diagrams.
Equipment for General Use — NH Master Electrician Exam Study Chapter
Learning Objectives
By the end of this chapter, you will be able to:
1.1 Scope and Structure of NEC Chapter 4
Chapter 4 of the 2023 NEC covers "Equipment for General Use." This is a broad category that includes wiring devices, switches, receptacles, lighting fixtures, motors, generators, transformers, and space-heating equipment. For the Master exam, you must not only know the individual requirements but also understand how these equipment rules interact with branch-circuit, feeder, and service calculations from Chapters 2 and 3.
The chapter is organized into articles:
For the Master license, the most heavily tested areas are Articles 404, 406, 408, 424, 430, and 450. You will be expected to apply these rules in the context of a complete installation, not just memorize individual code sections.
1.2 Flexible Cords and Cables (Article 400)
Flexible cords are permitted only for specific uses listed in 400.10. These include pendants, wiring of fixtures, connection of portable appliances, and connection of stationary equipment to facilitate interchange. A common master-level trap is the use of flexible cord as a substitute for fixed wiring — this is explicitly prohibited in 400.12.
Key points for the exam:
Master-level consideration: When supervising a temporary installation (Article 590), flexible cords are often used more liberally, but the same ampacity and protection rules apply. Temporary wiring must still comply with 590.4 for overcurrent protection.
1.3 Switches (Article 404)
Switches are categorized by their construction and application. For the Master exam, you must know the horsepower rating requirements for switches used in motor circuits.
Master-level consideration: When a switch is used to control a motor, the switch must open all ungrounded conductors simultaneously. For a 3-phase motor, this means a 3-pole switch is required. Single-pole switches on 3-phase motor circuits are a code violation.
1.4 Receptacles and Cord Connectors (Article 406)
Receptacle requirements are among the most frequently tested topics. For the Master exam, focus on the commercial and industrial applications, not just residential.
1.4.1 Receptacle Configurations
Receptacles must be of the proper configuration for their voltage and current rating (406.6). The NEMA configuration chart is referenced, but you must know the common ones:
Exam trap: A 20 A receptacle is not permitted on a 15 A branch circuit, but a 15 A receptacle is permitted on a 20 A circuit if the circuit supplies two or more receptacles (210.21(B)(3)). A single receptacle on an individual branch circuit must have an ampere rating not less than the branch circuit rating.
1.4.2 Receptacle Ratings for Motor Loads
When a receptacle supplies a motor load, the receptacle must have an ampere rating not less than the motor's full-load current. For a motor with a full-load current of 12 A, a 15 A receptacle is acceptable. For a motor drawing 18 A, a 20 A receptacle is required.
1.4.3 Grounding and Polarization
Receptacles must be grounded and polarized per 406.4. Replacement receptacles must be of the same type and rating as the original. A master must verify that replacement receptacles in older installations are grounded — if no equipment grounding conductor exists, a GFCI-type receptacle may be used and marked "No Equipment Ground" (406.4(D)(2)(b)).
1.4.4 Tamper-Resistant and Weather-Resistant
Tamper-resistant receptacles are required in all 125 V, 15 A and 20 A receptacles in areas accessible to children (406.12). Weather-resistant receptacles are required in wet or damp locations (406.9). For commercial kitchens and outdoor areas, both features are often required.
1.5 Switchboards and Panelboards (Article 408)
Panelboards are a critical area for the Master exam. You must understand the relationship between the panelboard rating, the main overcurrent device, and the number of circuits.
1.5.1 Panelboard Overcurrent Protection
Per 408.36, each panelboard must be protected on the supply side by an overcurrent device with a rating not greater than the panelboard's rating. A 200 A panelboard must be fed from a 200 A or smaller overcurrent device.
Exception: A panelboard may be fed from a larger overcurrent device if the panelboard is rated for the higher fault current and the supply conductors are protected at their ampacity. This is common in "main lug only" panels fed from a service disconnect.
1.5.2 Circuit Identification
Every circuit must be clearly identified at the panelboard (408.4). A master must verify that the directory is legible and accurate. This is a frequent inspection finding.
1.5.3 Phase Arrangement
For 3-phase panelboards, the phase arrangement must be such that the loading is balanced. While the NEC does not mandate a specific phase rotation, the master must ensure that the panelboard is marked with the system voltage and phase (408.3). A 208Y/120 V panelboard must not be used on a 240 V delta system unless it is listed for that purpose.
1.6 Fixed Electric Space Heating (Article 424)
Fixed electric space heating includes baseboard heaters, radiant heating cables, and heat pumps with electric resistance elements. For the Master exam, focus on the branch-circuit sizing.
1.6.1 Branch-Circuit Sizing
Per 424.3, fixed electric space heating equipment is considered a continuous load. Therefore, the branch circuit must be sized at 125% of the total connected load. A 10 kW heater at 240 V draws 41.7 A. The branch circuit must be rated at 52.1 A, which requires a 60 A circuit with conductors rated for at least 52.1 A (use 60°C column for terminations unless otherwise marked).
1.6.2 Multiple Heaters on One Circuit
Multiple heaters may be on one branch circuit, but the total load must not exceed the circuit rating after the 125% continuous load factor. A 20 A circuit can supply heaters totaling 16 A (20 A ÷ 1.25).
1.6.3 Clearances
Heaters must maintain clearance from combustible materials (424.9). The manufacturer's instructions govern, but a general rule is 12 inches from the floor and 6 inches from drapes or furniture. A master must verify that heaters are not installed below receptacles where cords could drape over the heater.
1.7 Motors and Generators (Articles 430 and 445)
Motor applications are the most complex area of Chapter 4. A Master electrician must be able to size conductors, overcurrent protection, and controllers for any motor installation.
1.7.1 Motor Full-Load Currents
Use Tables 430.247 through 430.250 to determine full-load currents. For a 3-phase, 460 V motor of 25 hp, Table 430.250 gives 34 A. Do not use the nameplate current for branch-circuit and feeder sizing — use the table values. The nameplate is used only for overload protection.
1.7.2 Branch-Circuit Conductors
Per 430.22, branch-circuit conductors must have an ampacity of 125% of the motor's full-load current. For the 25 hp motor above (34 A), conductors must be rated at 42.5 A. Using 75°C terminations, this requires 8 AWG copper (50 A at 75°C).
1.7.3 Overload Protection
Overload devices (heaters, electronic relays) are sized from the nameplate full-load current, per 430.32. The overload must be set at no more than 125% of the nameplate for motors with a service factor of 1.15 or greater, or a temperature rise of 40°C or less. For other motors, the maximum is 115%.
1.7.4 Short-Circuit and Ground-Fault Protection
The branch-circuit short-circuit and ground-fault protective device (typically a breaker or fuse) is sized per Table 430.52. For a 3-phase squirrel-cage motor, the maximum rating is 250% of the full-load current for inverse-time breakers, or 175% for non-time-delay fuses. The 25 hp motor at 34 A can have a breaker up to 85 A (34 × 2.5 = 85 A). A standard 90 A breaker would be too large; you would need to use a 80 A breaker or a fuse.
1.7.5 Motor Controllers
The controller must have a horsepower rating not less than the motor's rating (430.83). A 25 hp motor requires a controller rated for at least 25 hp. A controller with a higher horsepower rating is always acceptable.
1.7.6 Disconnecting Means
A motor disconnecting means must be within sight of the motor and controller (430.102). "Within sight" means visible and not more than 50 feet away. The disconnect must open all ungrounded conductors.
1.7.7 Generators (Article 445)
Generators are treated similarly to motors for conductor sizing. The ampacity of the generator output conductors must be at least 115% of the generator's rated output (445.13). Overcurrent protection must be provided per 445.12. A master must verify that a generator used as a separately derived system has the neutral bonded to ground at the generator only if it is the first disconnecting means.
1.8 Transformers (Article 450)
Transformers are a critical component of commercial and industrial installations. The Master exam will test your ability to size transformer overcurrent protection and understand the implications of transformer connections.
1.8.1 Overcurrent Protection
Per 450.3, transformers must be protected against overcurrent on both the primary and secondary sides.
Example: A 75 kVA transformer, 480 V primary, 208Y/120 V secondary. Primary full-load current = 75,000 ÷ (480 × 1.732) = 90.2 A. Primary protection at 125% = 112.8 A. A 110 A breaker is acceptable. Secondary full-load current = 75,000 ÷ (208 × 1.732) = 208 A. Secondary protection at 125% = 260 A. A 250 A breaker is acceptable.
1.8.2 Transformer Impedance and Fault Current
A master must understand that transformer impedance affects available fault current. A 75 kVA transformer with 5% impedance will have a short-circuit current of approximately 20 times its full-load current. This must be considered when selecting equipment with adequate interrupting ratings.
1.8.3 Separately Derived Systems
A transformer secondary is a separately derived system. The neutral must be bonded to the equipment grounding conductor at the transformer or at the first disconnecting means (250.30). The grounding electrode conductor must be sized from Table 250.66 based on the largest ungrounded conductor.
1.9 Code Navigation — Where to Find It
| Topic | NEC Reference |
|---|---|
| Flexible cord ampacity | Table 400.5(A)(1) |
| Flexible cord uses | 400.10 |
| Switch ratings | 404.14 |
| Receptacle configurations | 406.6 |
| Receptacle in wet locations | 406.9 |
| Tamper-resistant receptacles | 406.12 |
| Panelboard protection | 408.36 |
| Panelboard circuit identification | 408.4 |
| Fixed space heating branch circuits | 424.3 |
| Heater clearances | 424.9 |
| Motor full-load currents | Tables 430.247–430.250 |
| Motor branch-circuit conductors | 430.22 |
| Motor overload protection | 430.32 |
| Motor short-circuit protection | Table 430.52 |
| Motor disconnecting means | 430.102 |
| Generator conductors | 445.13 |
| Transformer protection | 450.3 |
| Separately derived systems | 250.30 |
1.10 Inspection and Supervision Points
As a Master electrician, you are responsible for the work of others. On site, verify the following:
1.11 Common Exam Traps
Summary
This chapter covers the core of NEC Chapter 4. As a Master candidate, you must be able to apply these rules in real-world scenarios — sizing conductors for a 3-phase motor feeder, protecting a transformer, and supervising the installation of receptacles and switches. The NEC is your primary reference during the exam, but you must know where to look and how to apply the tables. Practice navigating the code quickly, and always verify the latest amendments in the New Hampshire Laws and Rules, which may adopt or modify specific NEC sections.
Preparing for the New Hampshire Master Electrician license?
See the full licensing path, exam format, eligibility and application steps.
Ready to test this chapter?
Practice with exam-aligned questions and timed simulations.
Start Practicing Free