Motors & Controls
Master Electrician Practice study guide with diagrams.
Motors & Controls — Master Exam Study Chapter
For the Delaware Master Electrician Exam (DE-MST) — 2023 NEC (NFPA 70)
Learning Objectives
By the end of this chapter, you will be able to:
1.1 The Scope of Article 430 — Beyond the Nameplate
Article 430 is the single most referenced article for motors, yet it is also the most misunderstood. The critical distinction a master must make is between nameplate full-load current (FLC) and the table values in 430.247–430.250. The NEC tables are used for conductor sizing, short-circuit and ground-fault protection, and disconnecting means ratings. The nameplate is used for overload protection and for the actual connected load in feeder calculations.
Exam Trap: When a motor nameplate shows a current lower than the table value, you must still use the table value for branch-circuit conductor sizing. The nameplate value is only used for overload relay selection (430.32) and for the motor load in the feeder/service calculation (430.24 Exception 1 allows nameplate if it is larger than table).
1.2 Motor Branch-Circuit Conductors — 430.22
Single motor conductors must have an ampacity of 125% of the motor FLC from the appropriate table (430.22(A)). This is not a continuous load factor per se; it is a minimum sizing rule that accounts for the motor’s starting and running characteristics.
For multiple motors on one branch circuit (430.22(C)), the conductors must be sized at 125% of the largest motor FLC plus the sum of the FLCs of all other motors on that circuit.
Critical nuance: For a motor with a service factor of 1.15 or greater, or a temperature rise of 40°C or less, the branch-circuit conductors are still sized at 125% of the table FLC — the nameplate service factor does not change conductor sizing. However, the overload protection (430.32(A)(1)) may be set at 125% of nameplate for those conditions.
Supervision Point: On site, verify that the conductor ampacity is based on the 75°C column of the ampacity table (Table 310.16) when terminals are rated 75°C. A common error is using the 90°C column for the entire circuit — the 90°C column is only permitted for derating purposes, not for the final ampacity at the termination.
1.3 Overload Protection — 430.32
Overload protection is designed to protect the motor, the branch-circuit conductors, and the motor control apparatus from excessive heating due to running overloads and stalled rotors. It is not short-circuit protection.
Three tiers of overload protection:
The "next higher standard size" rule (430.32(C)): If the motor nameplate current multiplied by the percentage (125% or 115%) does not correspond to a standard fuse or heater size, you may go up to the next standard size. Standard sizes are listed in 240.6(A). For fuses and inverse-time circuit breakers, the next higher size is permitted. For adjustable trip relays, the next higher setting is permitted, but not to exceed the next standard size.
Exam Trap: The 125% overload rule applies to the nameplate, not the table FLC. If a motor nameplate says 10 A but Table 430.248 says 12 A, the overloads are set at 10 A × 1.25 = 12.5 A (next standard size up). The conductors are sized at 12 A × 1.25 = 15 A.
1.4 Short-Circuit and Ground-Fault Protection — 430.52
This is the device that protects the branch-circuit conductors, the controller, and the motor against short circuits and ground faults. It is not sized to protect the motor itself from overloads.
Maximum permitted ratings (430.52(C)(1), Table 430.52):
The "next higher standard size" rule for SC/GF protection (430.52(C)(1) Exception 1): If the calculated value (e.g., 175% of FLC) does not correspond to a standard fuse or breaker, you may go up to the next standard size. However, if the motor will not start with that size, you may go higher, but not exceeding 400% for non-time-delay fuses, 225% for dual-element fuses, and 400% for inverse-time breakers (Exception 2(b)).
Exam Trap: The 400% maximum for non-time-delay fuses and breakers is a hard ceiling. You cannot exceed it even if the motor stalls on start. The only exception is for motors that are part of an approved assembly where the manufacturer has listed specific protection.
Supervision Point: Check that the fuse size is marked on the disconnect or the controller. A common violation is installing a 30 A fuse where a 20 A dual-element fuse is required, because the installer used the next standard size incorrectly.
1.5 Motor Controllers — 430.81 to 430.90
A motor controller is any device that governs the electric power to the motor. This can be a manual motor starter, a magnetic contactor, a variable frequency drive (VFD), or even a general-use snap switch for motors rated 2 hp or less (430.83(C)).
Controller rating (430.83): The controller must have a horsepower rating at the applied voltage that is not less than the motor's horsepower rating. For a motor rated more than 100 hp, or for a controller rated more than 100 hp, the controller may be marked "100 hp" and used for any motor up to that rating if the controller has a current rating at least equal to the motor's FLC.
Controller for a motor with a VFD (430.120): The VFD itself is the controller. It must be rated for the motor's FLC and for the specific application (constant torque vs. variable torque).
Control circuits (430.71): Control circuits (e.g., start/stop pushbutton wiring) must be protected against overcurrent. If the control circuit is tapped from the motor branch circuit, the tap must have overcurrent protection rated no more than 300% of the control circuit conductor ampacity (430.72(B)(2)). If the control circuit is supplied from a separate source, it must have its own overcurrent protection.
Exam Trap: A control transformer supplying a 120 V control circuit from a 480 V motor branch circuit must have its secondary protected at no more than 125% of the secondary conductor ampacity (430.72(C)(5)). Many installers forget the secondary protection.
1.6 Disconnecting Means — 430.101 to 430.113
Each motor must have a disconnecting means that is capable of disconnecting the motor and the controller from all ungrounded supply conductors (430.102). The disconnect must be:
Exception for cord-and-plug-connected motors (430.109(C)): If the motor is cord-and-plug-connected and the plug/receptacle is within sight of the motor, the plug/receptacle may serve as the disconnecting means, provided it is rated for the motor's FLC.
Supervision Point: For a motor with a separate controller (e.g., a magnetic starter in a panel), the disconnect must be within sight of the controller and the motor. If not within sight of both, a second disconnect is required at the motor location.
1.7 Motor Feeder Sizing — 430.24 and 430.25
Motor feeders supply multiple motors. The feeder conductors must have an ampacity of 125% of the largest motor FLC plus the sum of the FLCs of all other motors on the feeder (430.24). This is the same rule as for multiple motors on a branch circuit, but applied at the feeder level.
Important interaction with Article 220: For service and feeder calculations under 220.50, the motor load is calculated at 125% of the largest motor plus the sum of all others. However, 220.50 also requires the largest motor 25% adder — which is effectively the same calculation. The key difference is that 220.50 applies to the service calculation, while 430.24 applies to the feeder calculation. For a master, the practical result is the same: the largest motor gets a 25% adder.
Feeder short-circuit and ground-fault protection (430.62): The feeder protection must be sized at the largest branch-circuit protective device rating for any motor on the feeder, plus the sum of the FLCs of all other motors. The "next higher standard size" rule does not apply here — you must use the next lower standard size if the calculated value is not standard.
Exam Trap: If you have a feeder with a 30 A branch-circuit fuse for motor #1 and a 20 A branch-circuit fuse for motor #2, the feeder protection is 30 A + (FLC of motor #2). If that sum is 42 A, you must use a 40 A fuse (next lower), not a 45 A (next higher).
1.8 Motor Loads in Service Calculations — 220.50
For a commercial or industrial service, motor loads are added to the general lighting and receptacle loads. The motor load is the largest motor FLC × 1.25 plus the sum of all other motor FLCs. This is the same 25% adder that applies to the largest motor.
Critical distinction: For a service supplying only motors (e.g., a pump house), the service conductors are sized per 430.24, not per the general Table 220.12 lighting load. The 25% adder is already built into 430.24.
Supervision Point: When reviewing a set of plans, verify that the service calculation includes the motor 25% adder. A common omission is adding the motor FLC at 100% and forgetting the 125% factor on the largest motor.
1.9 Generators and Separately Derived Systems — 445 and 700
Generators are treated as separately derived systems when they have no direct connection to the utility source (445.10). The generator's output conductors must be sized per the generator nameplate rating, not the prime mover rating (445.13). The generator must have a disconnecting means that is capable of carrying the full load current (445.18).
Overcurrent protection for generators (445.12): Generators must be protected against overloads and short circuits. If the generator is a standalone unit, the overcurrent device must be rated at not more than 115% of the generator's rated current. If the generator is connected to a bus with other sources, the protection must be coordinated with the other sources.
Exam Trap: A generator rated 100 kW at 480 V three-phase has a rated current of approximately 120 A (100,000 ÷ (480 × 1.732)). The overcurrent device must be rated at 115% = 138 A, so a 150 A breaker is the minimum standard size. Many installers use a 125 A breaker, which is too small.
Transfer switches (700.5): For emergency systems, the transfer switch must be listed for emergency use and must be mechanically held. The generator must be able to supply the emergency load within 10 seconds of a power failure (700.12).
1.10 Variable Frequency Drives (VFDs) — 430.120 to 430.130
VFDs are now the standard method for motor speed control in commercial and industrial applications. The NEC treats a VFD as both the controller and the overload protection device.
Key requirements:
Supervision Point: Verify that the VFD is programmed for the correct motor FLC. A VFD set to 10 A for a motor with a nameplate FLC of 12 A will trip on overload during normal operation. A VFD set to 15 A will not protect the motor.
1.11 Code Navigation — Where to Find It
| Concept | NEC Reference |
|---|---|
| Motor full-load currents (tables) | Table 430.247 (DC), 430.248 (single-phase AC), 430.250 (three-phase AC) |
| Branch-circuit conductors | 430.22(A), 430.22(C) |
| Overload protection | 430.32, 430.36 |
| Short-circuit/ground-fault protection | 430.52, Table 430.52 |
| Standard fuse/breaker sizes | 240.6(A) |
| Controllers | 430.81–430.90 |
| Disconnecting means | 430.101–430.113 |
| Motor feeders | 430.24, 430.25, 430.62 |
| Motor loads in service calc | 220.50, 220.14(C) |
| Generators | 445.10–445.18 |
| Emergency systems | 700.5, 700.12 |
| VFDs | 430.120–430.130 |
| Conductor ampacity tables | Table 310.16 |
| Continuous load factor (general) | 210.19(A)(1), 215.2(A)(1) |
1.12 Inspection and Supervision Points
As a master electrician, you are responsible for the final sign-off. On any motor installation, verify:
1.13 Common Exam Traps
1.14 Summary
Mastering motors and controls requires a clear separation of the three distinct protection functions — overload, short-circuit/ground-fault, and disconnecting means — and knowing which code table or nameplate value drives each calculation. The master electrician must also understand how motor loads integrate into the broader service and feeder calculations under Article 220. By memorizing the key percentages (125%, 115%, 175%, 250%, 300%) and the exceptions for next-higher sizes, you will be prepared for the calculation-heavy questions on the Delaware Master exam. Always verify the 2023 NEC adoption date (January 1, 2026, for Delaware) and use the current tables during the open-book exam.
Preparing for the Delaware Master Electrician license?
See the full licensing path, exam format, eligibility and application steps.
Ready to test this chapter?
Practice with exam-aligned questions and timed simulations.
Start Practicing Free