Chapter IV

Service, Feeders & Branch Circuits

Master Electrician Practice study guide with diagrams.

Service, Feeders & Branch Circuits

Learning Objectives

Upon completing this chapter, you will be able to:

4.Distinguish between service, feeder, and branch-circuit conductors and identify the applicable Code Articles for each.
5.Apply the NEC rules for service entrance conductor sizing, service disconnects, and grounding electrode system requirements for commercial and industrial services.
6.Calculate feeder and branch-circuit loads for continuous and non-continuous loads, including the 125% continuous load factor.
7.Understand the requirements for separately derived systems (transformers and generators), including grounding, bonding, and overcurrent protection.
8.Apply motor circuit conductor sizing, overcurrent protection, and disconnecting means rules per Article 430.
9.Recognize the principles of overcurrent protection coordination (selective coordination) as required for emergency, legally required standby, and critical operations power systems.
10.Identify common inspection failures and exam traps related to services, feeders, and branch circuits.

1.1 The Big Picture: System Architecture

The NEC organizes power distribution from the utility point to the outlet. A Service is the conductors and equipment that deliver electric power from the utility supply system to the service disconnecting means. A Feeder comprises all circuit conductors between the service equipment, the source of a separately derived system, or other power supply source, and the final branch-circuit overcurrent device. A Branch Circuit is the conductors and components between the final overcurrent device protecting the circuit and the outlet(s).

A master electrician must visualize this hierarchy on every job. The rules governing each segment are distinct, and mixing them up is a classic exam error. For instance, the ampacity adjustment factors of Article 310 apply to feeders and branch circuits, but service conductors have their own specific rules under Article 230.


1.2 Services (Article 230)

Service Anatomy: 230.42 Sizing and the Six-Disconnect Rule Service Anatomy: 230.42 Sizing & the Six-Disconnect Rule NEC 2023 • 230.42(A)(1) via 220.10 • 230.71(B) • 230.72(A) • 250.24(B) — Commercial Service Utility Source CT Cabinet Metering Service Point (230.70) Service Conductors Service Enclosure MBJ (250.24(B)) Bonded here Grounded Conductor (Neutral) Never bond downstream Service Disconnect Group — 230.71(B) Max 6 disconnects • 230.72(A) grouped at one location Disc. 1 250 A Disc. 2 200 A Disc. 3 100 A Disc. 4 60 A Disc. 5 30 A Disc. 6 20 A ⚠ Seven separate handles = Violation Unless a listed assembly (230.71(B) exception) Load Calculation — 230.42(A)(1) via 220.10 Continuous Load 160 A × 125% = 200 A Noncontinuous 40 A × 100% = 40 A + Total Calculated Load 240 A (200 A + 40 A) Conductor Selection 75°C column 250 kcmil Cu = 255 A per Table 310.16 Service Device 250 A Overcurrent 240.6 standard size To Branch Circuits BC1 BC2 GEC to Electrode per Table 250.66 Master Electrician Practice — NEC 230.42 service conductor sizing • Maine Electricians' Examining Board / Prov

Article 230 is the master’s guide to the service entrance. Key areas of focus for the exam and field supervision include the number of services, disconnects, and the specific rules for service conductors.

Number of Services (230.2): A building can be served by only one service, unless specific conditions are met. These include:

Fire pumps, emergency systems, legally required standby, or optional standby systems.
Continuous industrial processes where a separate service is necessary for shutdown.
Different voltage, frequency, or phase characteristics.
Multiple occupancy buildings with no available space for common service equipment.

Service Disconnects (230.71): The service disconnecting means must consist of not more than six switches or circuit breakers grouped in one location. This is the "six-handle rule." Each disconnect must be suitable for the maximum fault current available at its terminals. For a master, this means verifying the interrupting rating of the breakers matches the available fault current calculation.

Service Conductor Sizing (230.42): Service conductors must be sized to carry not less than the sum of the non-continuous loads plus 125% of the continuous loads. The minimum size for a service is 8 AWG copper or 6 AWG aluminum, but in practice, commercial services are far larger. The ampacity of the service conductors must be based on Table 310.16 (at 75°C for typical terminations) and adjusted for ambient temperature and conductor bundling per Article 310.15.

Service Grounding (250.24): The grounded conductor (neutral) from the utility must be connected to the grounding electrode system at the service. This is the single point of grounding. The grounded conductor must be routed with the phase conductors and is not permitted to be used for any other purpose. A common violation is bonding the neutral at a subpanel downstream of the service — this is strictly prohibited (250.142(B)).

Inspection Point: Verify that the service neutral is bonded to the service equipment enclosure via the main bonding jumper. Check that the grounding electrode conductor (GEC) is properly sized per Table 250.66 and connected to an acceptable electrode (ground rod, concrete-encased electrode, etc.) per 250.52.


1.3 Feeders (Article 215)

Feeder Sizing and Taps: 215.2 Math with 240.21 Escape Hatches Feeder Sizing and Taps: 215.2 Math with 240.21 Escape Hatches NEC 2023 • Maine Master Electrician • Chapter 4 — Service, Feeders & Branch Circuits STEP 1 — FEEDER MINIMUM AMPACITY NEC 215.2(A)(1) + 215.3 — feeder + OCPD sized together Subpanel loads: • 120 A continuous • 80 A noncontinuous (e.g. lighting + receptacles) Computed load: I = 100% × 80 A + 125% × 120 A = 230 A Conductor sizing (per Table 310.16): 230 A → 250 kcmil Cu @ 75°C = 255 A OCPD = 250 A (next standard, per 240.6) ⚠ Consider 215.2(A)(1) FPN: voltage drop ≥ 3% feeder — may require larger conductor for long runs. Feeder OCPD (215.3) = same 125%/100% calc → 250 A breaker protects the 250 kcmil conductor 400 A Main panel 250 kcmil 250 A OCPD Subpanel 230 A load STEP 2 — TAP ALTERNATIVES (240.21) Tap conductors = feeder without OCPD at supply end 240.21(B)(1) — 10 ft tap • ≤ 3 m (10 ft) length • Sized for connected load only • No OCPD at supply end • Must terminate in OCPD Example: 230 A load → 250 kcmil tap 240.21(B)(2) — 25 ft tap • ≤ 7.5 m (25 ft) length • Ampacity ≥ ⅓ of OCPD rating • Terminate in single OCPD • No splices (except at terminations) Example: 250 A ÷ 3 = 83.3 A → 3 AWG 10 ft tap 25 ft tap OCPD Load ⚠ TRAP: Spliced tap loses tap status — full feeder rules apply. KEY DISTINCTION — CONDUCTOR LENGTH vs. OCPD REQUIREMENT Full feeder (215.2): full ampacity + OCPD at supply 10 ft tap: load ampacity only, OCPD still at load end 25 ft tap: ⅓ OCPD rating, single OCPD at load end Master Electrician Practice — NEC 215.2 feeder sizing + 240.21 tap rules | Maine Master Electrician (2023 NEC)

Feeders are the workhorses of a commercial building, distributing power from the service to panelboards. The master is responsible for ensuring feeder conductors are properly sized for voltage drop and load.

Feeder Sizing (215.2): The minimum feeder conductor size must have an ampacity of not less than the non-continuous load plus 125% of the continuous load. This is the same calculation as for services. However, the minimum size is 14 AWG for copper and 12 AWG for aluminum, per 215.2(A)(1).

Voltage Drop (215.2(A)(1) Informational Note): While not a mandatory percentage, the FPN recommends that feeders be sized so the voltage drop does not exceed 3%, and the total drop for feeders and branch circuits combined does not exceed 5%. For a master, this is a practical design criterion. Long runs of feeders to rooftop units or remote panels are prime candidates for voltage drop issues. Oversizing the feeder by one or two sizes is a standard field solution.

Feeder Overcurrent Protection (215.3): Feeders must be protected against overcurrent. The rating of the feeder overcurrent device must not be less than the ampacity of the feeder conductors, but it can be higher if the next standard size (per 240.6) is used, provided the conductors are protected against overload.

Neutral Conductor (215.2(A)(2)): The neutral must be sized to carry the maximum unbalanced load. For a 3-phase, 4-wire wye system, this is the maximum load on any one phase. In many cases, the neutral can be smaller than the phase conductors, but it must never be smaller than the grounding conductor required by Table 250.122.

Exam Trap: Do not confuse feeder sizing with branch-circuit sizing. A feeder supplying a panelboard that feeds multiple branch circuits must be sized on the sum of the loads, not the rating of the main breaker in the panelboard.


1.4 Branch Circuits (Article 210)

Branch circuits are the final conductors. The master must understand the classification of branch circuits and the rules for multiwire branch circuits.

Classifications (210.3): Branch circuits are classified by the rating of the overcurrent device protecting them. Common ratings are 15, 20, 30, 40, and 50 amperes. The circuit’s rating dictates the minimum conductor size and the maximum connected load.

Continuous Loads (210.19(A)(1)): The ampacity of a branch-circuit conductor must be not less than the non-continuous load plus 125% of the continuous load. A continuous load is one where the maximum current is expected to continue for 3 hours or more. Lighting in commercial spaces is almost always considered continuous.

Multiwire Branch Circuits (210.4): A multiwire branch circuit consists of two or more ungrounded conductors that share a common grounded conductor (neutral). They must originate from the same panelboard. For a master, the critical rule is that all conductors of a multiwire branch circuit must be disconnected simultaneously by the branch-circuit overcurrent device. This means a 2-pole or 3-pole breaker is required, not individual single-pole breakers, unless the breakers are handle-tied.

Inspection Point: In a commercial kitchen or office, verify that multiwire circuits share a common trip breaker. A common violation is using two single-pole breakers with a handle tie, which does not provide common trip for a fault on one phase.

Branch Circuit Ratings (210.23): The total load on a branch circuit must not exceed the branch circuit rating. For a 15- or 20-amp circuit supplying multiple outlets, the load is limited to 80% of the rating if the load is continuous. For a circuit supplying a single appliance, the load can be up to 100% of the rating.


1.5 Separately Derived Systems (Article 250.30)

A separately derived system is a source of power that has no direct connection to the supply conductors, except through the grounding and bonding path. Common examples are transformers and generators.

Grounding (250.30(A)): The system must be grounded by connecting the grounded conductor (neutral) to a grounding electrode system at the source. This is a new grounding point, separate from the service. The GEC is sized per Table 250.66 based on the derived phase conductors.

Bonding (250.30(A)(2)): The grounded conductor must be bonded to the system enclosure (the transformer or generator housing) and to the equipment grounding conductor. This is done with a system bonding jumper.

Overcurrent Protection (240.21(C)): Transformer secondary conductors must be protected by an overcurrent device on the secondary side. The primary side overcurrent device can protect the secondary if the primary-to-secondary voltage ratio is considered, but the most common practice is a secondary breaker or fused disconnect.

Inspection Point: For a 480V-to-208Y/120V transformer, check that the neutral is bonded to the transformer case and a GEC is run to the nearest grounding electrode. A common error is treating the transformer like a subpanel and floating the neutral, which is a serious safety hazard.

Generators (702.4): For an optional standby generator, the transfer switch must be listed for the purpose. If the generator is a separately derived system (i.e., it has a transfer switch that opens the neutral), it must be grounded per 250.30. If it is a non-separately derived system (solidly connected neutral), the generator frame is bonded to the service neutral.


1.6 Motor and Generator Applications (Article 430)

Motors are a major load in commercial and industrial settings. The master must apply the specific rules of Article 430, which differ significantly from general lighting circuits.

Conductor Sizing (430.22): Motor branch-circuit conductors must have an ampacity of not less than 125% of the motor’s full-load current (FLC). The FLC is found in Tables 430.247 through 430.250, not on the motor nameplate. The nameplate is used for overload protection, but the tables are used for conductor sizing and short-circuit protection.

Overload Protection (430.32): Motors must be protected against overload. The overload device (heaters in a starter or an electronic overload relay) must be sized at not more than 115% to 125% of the motor nameplate current rating, depending on the motor’s service factor and temperature rise.

Short-Circuit and Ground-Fault Protection (430.52): The motor branch circuit must be protected by a fuse or breaker sized per Table 430.52. The maximum rating is typically 250% of the FLC for a time-delay fuse and 800% for an instantaneous trip breaker. If the maximum rating is not sufficient to start the motor, the next higher standard size is permitted.

Disconnecting Means (430.102): A disconnecting means must be located in sight from the motor and the driven machinery. "In sight" means visible and not more than 50 feet away. The disconnect must open all ungrounded conductors.

Exam Trap: Do not use the motor nameplate current for conductor sizing. Use the table values. The nameplate current is often lower than the table value, leading to undersized conductors.


1.7 Overcurrent Protection Coordination

Selective Coordination: When Only the Upstream Device Opens Selective Coordination: When Only the Upstream Device Opens NEC 2023 · 620.62, 700.32, 701.27, 517.30 · Master depth — series vs. selectively coordinated breakers ✓ SELECTIVELY COORDINATED Only upstream device opens — healthy loads stay powered UPSTREAM 400A opens — clears fault DOWNSTREAM 100A holds — does not trip feeder fault LOAD A LOAD B LOAD C Elevator feeder (620.62): full-range coordination required Emergency (700.32) · Legally required standby (701.27) ✗ NON-COORDINATED (series) Both devices trip — healthy loads black out UPSTREAM 400A trips — loses all loads DOWNSTREAM 100A also trips — nuisance feeder fault LOAD A LOAD B LOAD C Two identical breakers are NOT inherently selective Series rating (240.86) — check marked equipment Time-Current Curves — the coordination test For any fault current up to the available fault current, the upstream curve must clear before the downstream device unlatches. time (s) current (A) → upstream 400A downstream 100A margin ⚡ MASTER TRAPS • Identical breakers are not selective — curves must be compared at every fault level • Series rating (240.86) allows lower downstream only if marked & fault current never exceeds rating • Hospital essential systems (517.30) demand coordination for life-safety branch loads Master Electrician Practice — NEC 2023 selective coordination (620.62, 700.32, 701.27, 517.30)

Selective coordination is a design requirement for specific systems. It ensures that when a fault occurs, only the nearest overcurrent device opens, leaving the rest of the system energized.

Requirements (700.28, 701.27, 708.54): Selective coordination is mandatory for emergency systems (Article 700), legally required standby systems (Article 701), and critical operations power systems (Article 708). The master must ensure that the overcurrent devices are coordinated so that a fault on a branch circuit does not take down the entire feeder.

Practical Application: This often requires the use of current-limiting fuses or circuit breakers with adjustable trip settings. A master must review the time-current curves of the devices to verify coordination. This is a design function that is often overlooked but is a key inspection point for AHJs on healthcare and high-rise projects.


1.8 Code Navigation

ConceptArticle / Table
Services, generalArticle 230
Service disconnects230.70 – 230.71
Service conductor sizing230.42
Grounding, service250.24
Grounding electrode conductorTable 250.66
FeedersArticle 215
Feeder sizing215.2
Branch circuitsArticle 210
Continuous loads210.19(A)(1)
Multiwire branch circuits210.4
Separately derived systems250.30
Transformer secondary protection240.21(C)
Motor circuitsArticle 430
Motor FLC tablesTables 430.247–430.250
Motor overload430.32
Motor short-circuit protection430.52, Table 430.52
Selective coordination700.28, 701.27, 708.54
Standard OCPD ratings240.6
Conductor ampacity tablesTable 310.16

1.9 Inspection & Supervision Points

72.Service Neutral: Confirm the neutral is bonded to the service enclosure and not bonded at any downstream panel.
73.Grounding Electrode: Verify the GEC is continuous, properly sized, and connected to an approved electrode.
74.Panelboard Neutral Bar: In a subpanel, the neutral bar must be isolated from the equipment grounding bar. The equipment grounding conductors must be on a separate bar bonded to the enclosure.
75.Continuous Loads: Check that the calculated load on any 20-amp circuit does not exceed 16 amps for continuous lighting.
76.Motor Disconnects: Ensure the disconnect is within sight of the motor and is capable of being locked in the open position.
77.Transformer Bonding: Verify the secondary neutral is bonded to the transformer case and a GEC is installed.

1.10 Common Exam Traps

Nameplate vs. Table: Using motor nameplate current for conductor sizing instead of the FLC tables.
Continuous Load Factor: Forgetting to apply the 125% factor to continuous loads on branch circuits and feeders.
Six-Handle Rule: Assuming more than six disconnects are allowed for a single service without checking the exceptions.
Subpanel Neutral: Bonding the neutral and ground in a subpanel, which creates a parallel path for neutral current.
Voltage Drop: Ignoring voltage drop on long feeder runs, which is a design consideration but not a mandatory percentage in the code text.
Transformer Grounding: Treating a separately derived system as a service and grounding it at the main panel instead of at the source.

Preparing for the Maine Master Electrician license?

See the full licensing path, exam format, eligibility and application steps.

Read the Maine Master Electrician guide

Ready to test this chapter?

Practice with exam-aligned questions and timed simulations.

Start Practicing Free